Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
ScottishPower Renewables awarded NKT a turnkey contract in 2022 to supply and install the complete 320 kV HVDC export cable system for the 1.4 GW East Anglia Three project, covering both offshore and onshore sections that will form the East Anglia THREE OFTO transmission assets. The scope includes design, manufacture, and installation of the high‑voltage export cables using NKT’s cable‑laying vessel NKT Victoria over a total route length of approximately 2 × 147 km offshore and 2 × 37 km onshore.