Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cable installation for the 320 kV HVDC export system that will form the East Anglia THREE OFTO began in June 2025, when NKT started work on the 1.4 GW East Anglia Three project, supplying and installing the offshore export cables that run approximately 147 kilometres from the wind farm in the North Sea to landfall at Bawdsey in Suffolk, and then connecting to onshore cables towards the new converter station at Bramford. The works are being executed using NKT’s cable-laying vessel NKT Victoria under a turnkey contract covering the complete offshore and onshore cable system for ScottishPower Renewables’ East Anglia Three transmission assets.