Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In November 2022, RTE issued a contract notice seeking suppliers for the construction, delivery, and subsequent operations and maintenance of the offshore substation that will transmit power from the Dunkirk offshore wind farm to the French grid, initiating the formal procurement process for this key grid connection asset. The notice covers the full offshore substation package for the Dunkerque Export connection.