In its 2015 draft Decommissioning Programme, Dudgeon Offshore Wind Limited set out an indicative schedule showing decommissioning activities for the Dudgeon Offshore Wind Farm beginning around Q4 2038, consistent with the project’s 25‑year design life and the expectation that the wind farm will not be decommissioned for at least 25 years after becoming operational. The schedule envisages project management, engineering and initial preparation campaigns starting in late 2038 as the first phase of offshore decommissioning works.