Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Dudgeon Offshore Wind Limited awarded Visser & Smit Marine Contracting B.V. an EPCI contract valued at €110 million covering the engineering, procurement, construction and installation of the project’s inter-array cables and the installation of two 42 km submarine export cables, including horizontal directional drilling at the Weybourne landfall, with offshore export cable installation planned for 2016; these export cables later formed part of the Dudgeon OFTO transmission assets.