Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By July 2019, the 900 MW DolWin 6 offshore DC grid connection in Germany, owned by TenneT, was listed in a WindEurope policy paper drawing on ENTSO-E’s Ten-Year Network Development Plan data, which detailed DolWin 6 as a DC transmission project with an estimated CAPEX of €1,180 million and an average distance of 90 km to shore.