Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
For the DolWin6 network connection, Jan De Nul and Hellenic Cables plan to carry out the final connection and testing works in spring 2026 on three 155 kV HVAC grid connection cables between the Nordseecluster 1 and 2 offshore wind farms and the DolWin kappa platform, following completion of the Nordseecluster offshore substations.