On 15 October 2023, the 900 MW DolWin epsilon offshore converter platform for the DolWin5 grid connection departed Seatrium’s shipyard in Singapore aboard the heavy‑transport vessel Mighty Servant 1 for shipment to Aibel’s yard in Haugesund, Norway, after around three years of construction and more than ten million man‑hours, marking a major fabrication and delivery milestone prior to final outfitting and HVDC equipment installation.