Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Prysmian commenced DolWin5 cable installation: land portion completed 2022, Wadden Sea and nearshore 2022-2023, offshore segment completed 2023, project wrapped January 2024. First project where Prysmian executed full submarine installation in-house using Barbarossa I barge.