By the time of Breakbulk’s report, the final submarine cable link between the DolWin epsilon offshore converter platform and the German mainland had been successfully laid, marking completion of offshore export cable installation for the DolWin5 grid connection. Under its turnkey EPCI contract, Prysmian managed the entire offshore cable installation, with Jan De Nul’s cable‑laying vessel Isaac Newton executing the subsea laying operations.