Negative
Setback or risk materialised
Medium Impact
Significant progress or notable issue
On 7 November 2016, the 916 MW DolWin2 offshore HVDC grid connection went out of service after a series of unplanned automatic shutdowns, with the outage attributed to a fault somewhere in the HVDC cable, halting transmission from the Gode Wind 1, Gode Wind 2 and Nordsee One wind farms to shore.