Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 13 November 2020, the Dogger Bank C and Sofia Offshore Wind Farms finalised and issued the Code of Construction Practice (CoCP) Appendix 2.1 – Consent Boundaries for the onshore works, in compliance with Requirement 27 of the Dogger Bank Teesside A and B Development Consent Order 2015 (as amended) and TCPA #1 Condition 9. The document, marked as final and valid from this date, was distributed to Redcar and Cleveland Borough Council and formally approved and signed off by representatives of Dogger Bank C’s project company (Projco 3) and Sofia Offshore Wind Farm Limited.