Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2021, DEME Offshore was awarded the engineering, procurement, construction and installation (EPCI) contract for the 66 kV inter‑array cable system at Dogger Bank C, covering the supply and offshore installation of approximately 250 kilometres of inter‑array cables and associated accessories for the third 1.2 GW phase of the Dogger Bank Wind Farm.