On 12 November 2021, Dogger Bank Wind Farm awarded Seaway 7 ASA the contract for transport and installation of monopile foundations and transition pieces on the 1.2 GW Dogger Bank C phase, using its heavy‑lift vessel Alfa Lift, with installation to commence in 2024 after completing foundation installation on Dogger Bank A and B, and the award remaining subject to Dogger Bank C reaching financial close by the end of 2021.