Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Onshore cable installation civil works for the Dogger Bank C HVDC export route began in Q1 2022, starting construction of the onshore cable infrastructure that will connect the Redcar/Marske landfall to the converter station near Lazenby and onward to the National Grid Lackenby substation.