Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +2yr (Apr 2026): Energy Voice (Apr 2026) reports timeline pushed back, commissioning likely after 2027. SSE Renewables states completion in 2027. Offshore construction started Oct 2024 but turbine installation for Phase C not yet started. --- The Dogger Bank C HVDC transmission system, including the offshore platform, subsea export cable route and onshore converter station near Redcar/Lazenby feeding into National Grid at Lackenby, is planned to transmit first power to the GB grid in Q3 2025, enabling initial export of electricity from the 1.2 GW Dogger Bank C phase. This milestone follows onshore cable civils starting in Q1 2022, converter station construction from Q2 2022, and offshore export cable and platform installation works scheduled from 2024.