Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +2yr (Apr 2026): SSE Renewables states Dogger Bank completion in 2027. Energy Voice (Apr 2026) reports uncertain timeline for Phase C. Original Jan 2026 COD was based on pre-delay estimates. --- Full commercial operation of the Dogger Bank C offshore transmission system, comprising the offshore HVDC platform, export cables to Teesside and the onshore converter and 400 kV grid connection at Lackenby, is planned for Q1 2026, when the link is expected to export the entire 1.2 GW output of Dogger Bank C. Project documentation states that after first power in Q3 2025, Dogger Bank C will ramp up to full power by early 2026 as part of the overall Dogger Bank wind farm build-out.