Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
On 30 June 2021, NKT confirmed it had secured the contract to manufacture, deliver, and install more than 2×250 km of 320 kV HVDC onshore and offshore export power cables and accessories for Dogger Bank C, with its cable‑laying vessel NKT Victoria to perform the installation, subject to the project reaching financial close later in 2021.