Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By mid‑August 2024, Campaign 1 / Section 2 of the Dogger Bank C export cable installation, covering the offshore route between KP91 and KP175 including the Langeled and SEAL pipeline crossings and the DBB power cable crossing, had been completed as part of constructing the HVDC export link to Teesside.