Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By September 2025, Correll Electrical Engineering, part of SPIE Wind Connect, had been contracted by Deme Offshore NL B.V. to carry out 66kV inter-array cable termination and testing on 95 wind turbine generators and the offshore substation platform at the Dogger Bank B offshore wind farm, with works running from October 2024 to the present and including installation of a cable monitoring system.