Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The Notice to Mariners for Dogger Bank B inter-array cable installation indicates that the VIKING NEPTUN cable-lay campaign, including associated trenching support by C-INSTALLER, is scheduled to run from 5 October 2024 until 31 January 2025. This defines the planned completion date for the main inter-array cable installation operations at the Dogger Bank B offshore wind farm.