Ofgem confirmed that the Dogger Bank B offshore transmission link is being tendered under Offshore Transmission Owner (OFTO) Tender Round 11 and announced that four bidder groups had been shortlisted at the Enhanced Pre-Qualification stage to proceed to the Invitation to Tender in 2025. The Dogger Bank B OFTO link, which will connect 1.2 GW of generation capacity, has an estimated asset value of £919.3 million, and the eventual OFTO licensee will receive a regulated revenue stream under its transmission licence, subject to asset availability.