Dogger Bank Windfarm Limited reported in its Weekly Notice of Operations dated 20 April 2026 that all Wind Turbine Generators have now been installed on the Dogger Bank A (DBA) offshore wind farm, marking completion of the turbine installation campaign and a transition of work on DBA to commissioning and maintenance operations.