Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2020, Dogger Bank Wind Farm signed its first turbine transport and installation contracts (packages A and B) with Jan De Nul Group, covering installation of 95 GE Haliade‑X turbines at Dogger Bank A and 95 at Dogger Bank B. A subsequent July 2021 announcement for Dogger Bank C noted that this third contract award followed the 2020 signature of the A and B packages, and confirmed that Jan De Nul’s next‑generation jack‑up vessel Voltaire would carry out turbine installation across all three phases.