Low Impact
Minor progress or informational
On 16 September 2025, the Department for Energy Security & Net Zero launched a further consultation on a proposal to extend the existing transmission licence exemption for the Dogger Bank A offshore transmission assets by 364 days to 18 December 2026. The consultation sought views on an amendment order to maintain Dogger Bank Offshore Wind Farm Project 1 Projco Ltd’s ability to transmit electricity over the Dogger Bank A transmission system while turbine installation, compliance testing and OFTO transfer are completed.