Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Offshore works at the landfall for Dogger Bank A and B commenced as part of the early offshore construction programme, preparing the coastal cable corridor ahead of export cable installation which began in April 2022. Nearshore UXO clearance licences were granted in April and July 2021. Note: Q4 2020 date is from pre-event decommissioning programme (May 2020); actual offshore landfall works likely started 2021 based on UXO licence timeline.