Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
RTE announced it had completed high-voltage testing and verification of the Dieppe–Le Tréport grid connection, including the Grande-Sole 225/400 kV substation at Petit-Caux and the double 225 kV subsea and underground links. Following these tests on the two submarine circuits, the connection was placed at the disposal of the wind farm producer several weeks ahead of schedule, ready to transport electricity from the future offshore wind farm for around 850,000 people.