Cables laying started in July 2013 by Van Oord; around half of cables laid before stoppage. Project record total: 33 kV MVAC array cables, 108 km route.
Van Oord started the DanTysk inter-array cable-laying works in July 2013, completing around half of the cable installation before operations were stopped in the autumn, after which the remaining scope was re-contracted.