DanTysk OWF array cable installation; 88 infield cables; terminations on 35 already installed and installation/termination of remaining 53. Project record: 33 kV MVAC array cables, 108 km total route.
Boskalis was contractor for inter-array (infield) cable installation works at the DanTysk offshore wind farm. After cable activities started in July 2013, Boskalis was called in during February 2014 to complete termination work on 35 already-installed infield cables, and then resumed installation and termination work for the remaining cables from April 2014, using the DP3 vessel Protea for terminations and the cable-laying vessel Olympic Taurus for cable installation.