Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of all 80 Siemens SWT‑3.6‑120 turbines at the 288 MW DanTysk offshore wind farm was completed by August 2014, following an offshore installation campaign that ran from April to August 2014. The turbines were transported and installed using Swire Blue Ocean’s Pacific Osprey jack-up vessel.