Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By mid-December 2013, all 80 monopile foundations and transition pieces for the DanTysk offshore wind farm had been installed in the German North Sea, completing the foundation installation campaign after around nine months of offshore construction. The work was carried out using the Seafox 5 jack-up vessel for owner DanTysk Offshore Wind GmbH.