Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In February 2014, Boskalis was engaged as contractor by DanTysk Offshore Wind to complete termination work on 35 already installed inter‑array cables and to install and terminate the remaining 53 of the 88 infield cables at the DanTysk offshore wind farm, using the DP3 vessel Protea for terminations and the Olympic Taurus for cable installation during the 2013–2014 construction campaign.