Cyclades Interconnection Phase D : Serifos - Milos
September 2023
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
IPTO’s financial reports state that in September 2023 contracts were signed for the High Voltage GIS substations on Folegandros, Milos and Serifos, moving the entire Phase D Cyclades interconnection into the construction phase. These substations provide the onshore connection points for the new 150 kV cables, including the Serifos and Milos substations that anchor the Serifos–Milos submarine interconnector.