Cyclades Interconnection Phase D : Serifos - Milos
Date TBD
Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Energypress reported that TERNA and a consortium of Nari and Electromec were named provisional winners of an IPTO tender to develop new high-voltage substations on Folegandros, Milos and Serifos, which form part of the fourth phase of the Cyclades interconnection and will host the terminations of the 150 kV links including the Serifos–Milos submarine cable. The article noted that interested parties had faced a 6 July 2022 bid deadline and that IPTO aimed to have the substation contracts signed by June following evaluation of the offers.