Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
ADMIE Holdings FY2025 report (April 2026): Lavrio-Serifos cable laid Feb 2024, Serifos-Milos cable laid May 2024, protection for both completed July 2024. Substations progressing. SW Cyclades integration targeted H2 2026.