Cyclades Interconnection Phase D : Milos - Folegandros
18 November 2022
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
IPTO (Independent Power Transmission Operator) awarded a contract on 18 November 2022 for the study, supply and installation of 150 kV underground and submarine XLPE cables for several Cyclades Phase D links, including the Milos–Folegandros section. The contract, awarded to Fulgor and Prysmian Powerlink, covers the Milos–Folegandros and Folegandros–Thira transmission lines, with Prysmian later describing an approximately €150 million turnkey scope to link Milos, Folegandros and Santorini under Phase D of the Cyclades interconnection project.