Cyclades Interconnection Phase A : Lavrio (Mainland) - Syros
2016
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Evidence from Asso.subsea's project reference list shows that for the Cyclades Project (Lavrio–Syros) – Lavrio and Syros sections, Prysmian/Asso.subsea carried out cable protection and landing assistance activities in 2015–2016, with no later years listed. Given that these works are performed after or alongside laying and that the Lavrio–Syros Phase A interconnector was in commercial operation by May 2018, this indicates that submarine cable installation and protection were completed by 2016, consistent with the original plan but with an imprecise completion day.