Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Ignitis Group indicates that the final investment decision (FID) for the 700 MW Curonian Nord offshore wind farm is expected only after 2027, following completion of development activities, obtaining a construction permit targeted around 2027, and securing external financing. The developer links the FID timing to improved visibility on long-term power offtake amid delays to large-scale electrolysis projects and uncertainty around an interconnector with Germany, which may also push back the project’s commercial operation date.