Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
The shallow geotechnical survey programme for the Culzean Floating Offshore Wind Turbine Pilot Project was concluded by April 2023, completing vibrocore and CPT investigations at the three planned mooring locations and along the cable corridor to the Culzean CPF platform. These March–April 2023 data sets are referenced in later project documentation as completed site investigations used to refine the cable route and confirm suitable ground conditions for the floater moorings and subsea cable installation.