Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
According to IPTO Holding’s 2022 corporate presentation, the 150 kV AC Crete–Peloponnese interconnection (2×200 MVA, two 132 km XLPE submarine cables plus underground sections) was commissioned in the first half of 2021, completing testing and commissioning activities required to bring the link into operational service.