On 25 June 2025, IPTO announced that the Crete–Attica HVDC submarine interconnection had successfully transferred 320 MW of electric power from Crete to Attica via the Ariadne Interconnection, demonstrating the link’s capability for bidirectional energy flows under real operating conditions while ongoing tests aim to reach maximum transmission capacity per cable.
On 24 May 2025, the Crete–Attica HVDC interconnector transmitted direct current electricity between Crete and mainland Greece for the first time, marking the start of trial operation. Following converter station energisation on 21 May 2025, IPTO’s subsidiary Ariadne Interconnection began sending power across the 1 GW, ±500 kV subsea link, with trial operations scheduled to continue through the summer to progressively test bidirectional power flows and ramp toward full capacity.
The Attica–Crete interconnector was officially placed in operation and fully commissioned on 24 May 2025, integrating Crete into the Greek national power grid via a 500 kV, 1 GW HVDC link. Developed by IPTO subsidiary Ariadne Interconnection with one 500 MW subsea cable system supplied by Nexans and the other by Prysmian, the project entered operational service on this date, after which trial operation continued through the summer for further performance verification.
Licence: Environmental permit / approval of environmental conditions (AEPO) for the 150 kV Chania–Damasta transmission line
An environmental permit (approval of environmental conditions, AEPO) was granted for the new 150 kV Chania–Damasta transmission line in western Crete, a supporting asset essential for the optimal combined use and simultaneous operation of Crete’s two interconnections with mainland Greece (Attica and Peloponnese). This permit approval enables construction and operation of the line, which will strengthen the Cretan transmission network linked to the Crete–Attica HVDC interconnector.
By early 2025, intensive equipment tests on the Crete–Attica HVDC link had enabled the new 150 kV Damasta substation in Crete to be successfully connected to the island’s AC grid, confirming commissioning of this onshore substation. At the same time, the 500 kV underground and subsea cables between the Attica and Crete converter stations were fully tested, preparing the interconnector for subsequent energisation and trial operation.
On 17 July 2024, Greece’s Ministry of Economy and Finance decided to include the second stage of the Crete–Attica interconnection in the NSRF 2021–2027 Operational Programme "Environment and Climate Change", approving funding of up to €222.3 million as part of total EU co‑financing for the project that can reach €535.5 million.
€222.3M (grant)
As reported in February 2024, the underground section of the Crete–Attica electricity interconnection between mainland Greece and Crete had been completed, allowing project activities to shift focus to constructing the converter stations at Damasta in Crete and Koumoundouros in Attica.
By 31 December 2023, the first stage of the Crete–Attica electrical interconnection (Phase II of Crete’s connection to the Hellenic grid) had been funded with €300.2 million from Greece’s NSRF 2014–2020 Operational Programme "Infrastructure, Environment and Sustainable Development", including an ERDF contribution of €250.6 million confirmed by the European Commission.
€300.2M (grant)
By 2023, Nexans had completed design, manufacturing, subsea installation and Site Acceptance Testing for its 500 MW, 500 kV HVDC subsea cable system forming half of the 1,000 MW Crete–Attica bipole interconnection between Attica and the Heraklion area of Crete.
In 2021, Ariadne Interconnection and the European Investment Bank signed a €200 million, 20‑year loan agreement (with a €100 million extension option) for the Crete–Attica interconnection, guaranteed by the Greek state, making EIB an equal co‑financier alongside Eurobank and strengthening the project’s financing terms.
€200M (debt)
| Heraklion (Crete) | Attica | |
|---|---|---|
| Landfall | Korakia, Heraklion (Crete) | Pachi, Megara (Attica) |
| Grid Connection | Damasta 150 kV GIS substation / Damasta Converter Station (connection into Crete transmission system) | Koumoundouros Extra‑High Voltage Center (Koumoundouros substation / Koumoundouros EHV Center) |
Heraklion (Crete)
Attica