Continental Link Multi-Purpose Interconnector
Date TBD
Negative
Setback or risk materialised
High Impact
Major milestone or critical setback
National Grid Ventures’ Continental Link Multi-Purpose Interconnector project has been marked as withdrawn on the UK National Infrastructure Consenting (Planning Inspectorate) portal, indicating that the planned Development Consent Order application for electric lines connecting to the Creyke Beck substation in East Yorkshire is no longer being progressed through that consent process.