On 6 September 2024 Codling Wind Park’s developers submitted a planning application to An Bord Pleanála for the overall Codling Wind Park project, including between 60 and 75 turbines on Codling Bank and the full transmission system comprising three offshore substations, three 220 kV offshore export cables to a landfall on the southern Poolbeg Peninsula, onshore 220 kV export cables, a new onshore substation north of Pigeon House Road, and onward connection into the existing Poolbeg 220 kV substation. The application, subject to Environmental Impact Assessment, seeks a 10‑year conditional planning permission with a 25‑year operational life and is due for decision by 1 April 2025.