COBRAcable entered commercial operation on 7 September 2019, when the 700 MW HVDC interconnector between Eemshaven (Netherlands) and Endrup (Denmark) became available for day-ahead and intraday electricity market trading. The link had completed its testing and commissioning period from 3 July to 6 September 2019. Shadow auctions via the Joint Allocation Office went live on 6 September 2019 for first delivery on 7 September. An official inauguration ceremony was held later on 4 November 2019. The project is jointly owned and operated by TenneT (Netherlands) and Energinet (Denmark).