ESB completed laying the submarine power cables linking Inishbofin and Clare Island to the Irish national grid, using a cable-laying vessel to install approximately 20 km of cable weighing about 600 tonnes at a rate of 1.5–3 km per hour, with offshore offloading and shoreline haul-in operations described.