Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cerulean Cedar plans to begin offshore construction in 2027, the year following the planned FID in 2026. Per Cerulean Winds' programme guidance, Cedar follows sister project Aspen by approximately one year (Aspen FID 2026, construction 2028); for Cedar, FID 2026 implies construction commencement in 2027 ahead of the targeted first power in 2028. Year precision reflects phase-level scheduling in current developer communications. The project remains pre-consent: offshore Section 36 and Marine Licence applications have not yet been submitted, so this projection is contingent on successful consenting.