Cerulean Aspen targets turbine installation in 2029 as part of the four-year offshore construction phase running 2028-2031 per the Feb 2026 EIAR Addendum. For a 1 GW TOG floating wind farm with 72 turbines using tow-to-port hook-up onto previously deployed semi-submersible foundations at Haventus' Ardersier facility, turbine installation typically follows foundation pre-installation by 6-12 months and precedes Phase 1 first power by 6-12 months, placing turbine installation start in 2029 between 2028 foundation deployment and 2029 Phase 1 first power. Year precision reflects phase-level scheduling.