Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cerulean Aspen plans to begin floating foundation installation in 2028 at the start of the offshore construction phase. The February 2026 EIAR Addendum confirms construction is anticipated to span up to four years with offshore works expected approximately 2028-2031; the project page also reiterates 'Aspen Offshore construction starts in 2028'. As a 1 GW TOG floating offshore wind farm with up to 72 semi-submersible foundations and multi-point moorings (up to six lines, radii up to 1,200 m) in the Central North Sea, foundation installation (anchor pre-lay and mooring deployment plus tow-out of floating foundations from Haventus' Ardersier Energy Transition Facility) is the first major offshore construction activity and is scoped to the 2028 commencement. Year precision reflects phase-level scheduling.