Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 17 February 2026, prefectural order no. 26-034 granted RTE an environmental authorisation for the creation and operation of certain works forming the grid connection of the Centre Manche 1 offshore wind farm in the Manche department, subject to mitigation, compensation, and monitoring measures specified in the order and its annexes.