Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
System commissioning and testing at the Irish converter station were planned to begin in 2026. EirGrid’s March 2026 Celtic Interconnector newsletter states that commissioning works to validate and test the installed high-voltage electrical equipment at the Ballyadam converter station "have commenced", confirming that the testing phase started by March 2026.